Projects Tracker

Major infrastructure projects monitored by timeline, budget, and completion status. Data from MoSPI, ministry dashboards, and parliamentary questions.

Projects Monitored

10

Total Cost

₹25.3L Cr

Avg Progress

58%

On Track

6

On Track

6

60% of total

Delayed

2

20% of total

At Risk

1

10% of total

Completed

1

10% of total

All ProjectsOn TrackDelayedAt RiskCompletedUnder ₹50,000 CrOver ₹1L Cr
Delhi-Mumbai Expressway

Road Transport · ₹1.0L Cr · Deadline: 2026

On Track
Progress72%
Budget: ₹1.0L CrProgress: 72%Deadline: 2026
Dedicated Freight Corridor (Eastern & Western)

Railways · ₹1.1L Cr · Deadline: 2025

On Track
Progress88%
Budget: ₹1.1L CrProgress: 88%Deadline: 2025
High Speed Rail (Mumbai-Ahmedabad)

Railways · ₹1.1L Cr · Deadline: 2029

Delayed
Progress42%
Budget: ₹1.1L CrProgress: 42%Deadline: 2029
Gati Shakti Terminal Redevelopment (125+ stations)

Railways · ₹50,000 Cr · Deadline: 2027

On Track
Progress35%
Budget: ₹50,000 CrProgress: 35%Deadline: 2027
Smart Cities Mission (100 cities)

Housing & Urban Affairs · ₹2.05L Cr · Deadline: 2026

On Track
Progress78%
Budget: ₹2.05L CrProgress: 78%Deadline: 2026
National Waterways Development (NW-1)

Ports & Shipping · ₹15,000 Cr · Deadline: 2028

Delayed
Progress28%
Budget: ₹15,000 CrProgress: 28%Deadline: 2028
Bharatmala Pariyojana Phase I & II

Road Transport · ₹10.6L Cr · Deadline: 2028

At Risk
Progress55%
Budget: ₹10.6L CrProgress: 55%Deadline: 2028
Sagarmala Port Modernization

Ports & Shipping · ₹8.6L Cr · Deadline: 2030

On Track
Progress44%
Budget: ₹8.6L CrProgress: 44%Deadline: 2030
UDAN Regional Connectivity Scheme

Civil Aviation · ₹4,500 Cr · Deadline: 2027

On Track
Progress62%
Budget: ₹4,500 CrProgress: 62%Deadline: 2027
PM GatiShakti National Master Plan

DPIIT · ₹100 Cr (IT) · Deadline: 2025

Completed
Progress75%
Budget: ₹100 Cr (IT)Progress: 75%Deadline: 2025