With 7.4 GW operational and 8 GW under construction, India's Nuclear Energy Mission targets 100 GW by 2047. We examine the fleet, planned reactors, and the road ahead for small modular reactors.
2026–2027
Gorakhpur Unit 1 & 2 (2 x 700 MW PHWR) commissioned
High probability2027–2028
Kudankulam Unit 5 & 6 (VVER-1000) grid synchronisation
Medium probability2028
First Bharat Small Reactor (BSR) deployment at retiring coal site
Medium probability2030
India-France Jaitapur EPR project final investment decision
Low-Medium probability2031
Nuclear Liability Law amendments expected to attract private investment
Medium probability2047
Target: 100 GW nuclear capacity for Viksit Bharat
Aspirational probability